40 Degrees Uphill: Gripper TBM Completes Second Tunnel for Limmern Hydropower Plant
Apr 29, 2013
In March 2013 a tunnel boring machine from Herrenknecht successfully completed excavation of the second headrace tunnel for the new pumped storage power plant at Limmern (Switzerland). Equipped with a new safety concept for securing the machine, the Gripper TBM was able to cope with the 40 degree gradient of the two tunnels without incident.
A Herrenknecht Gripper TBM (Ø 5,200 mm) bored two 1,030 meter long headrace tunnels through hard rock, connecting the upper reservoir to the machine hall cavern. With the breakthrough of the second tunnel on March 13, 2013 another key milestone in the major project »Linthal 2015« was reached. Linthal is expected to commence operations in 2015 as the currently largest hydroelectric power project in Switzerland. In cooperation with the construction company, Swiss firm Marti Tunnelbau AG, the engineers from Herrenknecht AG developed a solution for safe tunnelling at a gradient of 40 degrees.
The machine drove two 1,030 meter long headrace tunnels from the underground cavern for the pump turbines (1,700 m above sea level) up to the 600 meters higher service chamber on the shores of the Muttsee lake. The tunnel route runs predominantly through Quintner limestone at depths of up to 565 meters. The Gripper TBM had to cut through rock strengths of up to 120 MPa. A route gradient of 40 degrees (equivalent to 84.7 percent) was a special challenge for the machine technology, the workers on site and the planning team. In both tunnels the specialists from Marti Tunnelbau AG had to pass through the Mörtalbruch fault zone. Complex supporting and rock stabilization measures slowed the advance but assured the final success of the project.
40 degrees uphill: tunnelling under extreme conditions.
The immense gradient called for an extremely reliable safety concept to hold the machine securely in place during tunnelling. At all costs it had to be ensured that the TBM could not slip back when the grippers were moved. For the Linthal project the construction company Marti Tunnelbau AG and Herrenknecht AG developed a double anti-reverse lock with full back-up redundancy of the available bracing levels for the 130 meter long and 800 tonne TBM. This significantly increased safety for man, machine and structure: in all operating states (advance, standstill or regripping) there were always at least two of three locking systems independently braced against the mountain. The anti-reversing locking systems worked mechanically on the basis of a self-locking toggle lever (automatic mechanical wedging). This meant that even in the case of a failure in the energy supply and the hydraulic systems the necessary bracing of the machine against the mountain was assured.
In November 2010 the Herrenknecht Gripper TBM began driving the first tunnel and completed it in October 2011 after best performances of up to 130 meters per week. Then the TBM cutterhead was disassembled and the back-up pulled back through the pressure shaft and made ready to go again. From February 2012 the TBM bored its way through the second tube and was still able to achieve a weekly best performance of 133 meters at the end of the tunnel in mid March 2013.
Pumped storage power plants: gigantic stores for clean energy.
The Muttsee, Tierfehd and Linthal (Canton of Glarus, Eastern Switzerland) hydroelectric power plants of Kraftwerke Linth-Limmern AG currently generate a total of 480 MW of clean energy. As part of the »Linthal 2015« project, the new Limmern pumped-storage plant will raise the capacity by 1,000 MW. Construction of the new power station is being carried out by the consortium ARGE Kraftwerk Limmern under the leadership of contractor Marti Tunnelbau AG.
Pumped storage power plants act as gigantic energy stores. They compensate for fluctuations in the power grid and ensure security of supply in the expansion of renewable energy sources. Immediately more power is available in the grid than is needed, the pumps of the new Limmern power station will pump water from the lower Limmernsee lake to the upper Muttsee lake. At peak hours, the water flows back to Limmernsee lake through two headrace tunnels to the pump turbines, which then generate environmentally friendly electricity.
More News and Articles
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Maintaining aging potable water pipe infrastructure is a constant challenge …
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation …
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
A new group of startups …
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking …
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Water …
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Utah State University (USU) has published new research on water main breaks in the United States and Canada, examining …
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) …
Mar 22, 2024
News
A superior HDD offering
Building on its relationships with leading horizontal directional drilling companies, TRACTO Australia has delivered three new rigs to operator Superior HDD.
Based in New South Wales, Superior HDD specialises in horizontal …
Mar 20, 2024
News
New portable water filtration technology could improve access to clean drinking water worldwide
The University of Texas at Austin has developed an injectable water filtration system with the aim to aid the over two billion people worldwide who …
Contact
Herrenknecht AG
Achim Kühn
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 (0) 7824 / 302-5400
Fax:
+49 (0) 7824 / 302-4730