Successful Reuse of AVN Machine in France
Jun 11, 2018
In the little French town of Plobsheim near Strasbourg, a joint venture consisting of the contractors Valentin and SMCE Réha has modernized the municipal drinking water system. Several pipe jacking drives were carried out using an AVN1200 microtunnelling machine. The longest section runs through groundwater in a noncohesive geology and crosses under a busy highway. Since the beginning of 2018 the Plobsheim well has been connected to the urban grid.
To ensure that the supply of drinking water in the Greater Strasbourg area (France) is guaranteed in future too, the supply line of a new well in the district of Plobsheim has been connected to the city's pipeline network.
The construction project "Champ captant d'alimentation en eau potable au sud de l'aglomération Strasbourgeoise" ("Drinking water production in the south of the metropolitan area of Strasbourg") included four underground pipe jacking drives.
In Plobsheim these sections were between 50 and 215 meters long and ran under the groundwater level. The French contractors Valentin and SMCE Réha opted for a slurry-supported AVN machine from Herrenknecht due to the water-bearing ground conditions in coarse gravel and sand, typical of the plains in the upper Rhine valley.
Valentin and SMCE Réha have been working closely with Herrenknecht in Europe for more than 20 years, operating multiple pipe jacking machines and containers in their own machine park. The AVN M-1188M has already been used in several projects. For the pipe jacking drives in Plobsheim, at Herrenknecht's Schwanau headquarters the machine was comprehensively refurbished and adapted to the requirements of the project.
The diameter of the AVN1200 was expanded from 1,505 mm to 1,740 mm and it was equipped with a new mixed-soil cutterhead. "For challenging projects we rely on high quality machine technology from Herrenknecht, which has proven itself again and again over many years.
And for special requirements we often find solutions together," say José Pereira, longtime site manager at Valentin and Guillaume Huntziger, site manager for SMCE Réha.
In Plobsheim, this partnership has proven itself once again: the longest drive at 215 m runs directly under a busy highway. In order to avoid damaging the road, pipe jacking operations had to be constant.
Otherwise, if the TBM stands still for longer periods, minor heave or settlement can occur on the surface. In 2-shift operation, the drive under the highway was carried out without interruptions. After less than a month, the machine finally reached the target shaft.
The experienced tunnelling crew also mastered the three other drives with flying colors. By the end of October 2017, all 470 meters of tunnel had been completed to the satisfaction of the client – the city of Strasbourg. Since the beginning of 2018, the new well has been connected to the pipeline network and supplies the inhabitants with drinking water.
Project Data Successful reuse of AVN machine in France
MACHINE DATA M-1188
Machine type: AVN1200
- Excavation diameter: 1,740 mm
- Max. torque: 195 kNm
PROJECT DATA
- Tunnel length: 470 m in total (4 drives between 50 and 215 meters in length)
- Application: Water
- Geology: Gravel, sand, boulders
- Customer: VALENTIN environnement & travaux publics / SMCE Réha Joint Venture
- Client: City of Strasbourg
More News and Articles
Apr 24, 2024
News
Sustainable drainage solutions: German Start-up transforms urban water management.
Germany boasts a well-established infrastructure for managing rainwater and wastewater, yet many developing countries lack such systems. Addressing this gap, …
Apr 22, 2024
News
HDD tooling that gets the job done
Horizontal directional drilling is a dynamic process that constantly changes and adapts to suit a range of applications across utilities and infrastructure. Operators looking to get the most from their equipment …
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Maintaining aging potable water pipe infrastructure is a constant challenge …
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation …
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
A new group of startups …
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking …
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Water …
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Utah State University (USU) has published new research on water main breaks in the United States and Canada, examining …
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) …
Contact
Herrenknecht AG
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 7824-302-5400