Rob Carr passes midpoint on Quinns Main Sewer
Jan 13, 2023
Rob Carr continues to kick goals on the construction of the Quinns Main Sewer project for Water Corporation with approximately half of the project now complete.
A combination of micro tunnelling and open trench pipe laying will be used to construct a 1.9 km wastewater pipeline with an internal diameter of 1.8 m, including one of the longest micro tunnelled drives carried out in WA. When completed this will enable the transfer of wastewater from the adjacent area to the Alkimos Wastewater Treatment Plant in accordance with the long-term wastewater distribution system plan.
The project commenced construction activity in February 2022, and has swiftly seen the completion of two of the four major micro tunnelled drives. The first drive of 190 m was completed in May with the second 312 m drive successfully completed in mid July 2022. Both drives were predominately through solid limestone conditions and were completed on time.
During this time, construction was also ongoing and since completed for the 24 m deep shaft required for the longer 637 m curved drive. Shaft 2097 was constructed using a combination of in situ concrete caisson sinking and underpinned precast segment techniques. The construction method was altered to suit the varying ground conditions encountered during the construction of the shaft.
Work has since commenced on our 3rd drive, some 630m long with our tunnel boring machine “Bakton launched from this same 24 m deep shaft. Bakton is 200m into its journey and crossed the Joondalup rail line and the Mitchell Freeway during a planned rail shutdown in late August 2022.
The 630 m drive also consists of a 600 m radius curve which necessitated the use of a VMT guidance system with the drive traversing through the most challenging ground conditions on the project where the machine will tunnel through a combination of sand and soft to hard pinnacle limestone.
Other works on the project consisted of a 400 m open trench section of sewer pipeline, which has been since has been laid with welding of the PVC pipe liner and access shaft construction now underway for that section of work.
Following completion of the tunnelling, construction will commence on the 27 m deep vortex manhole. The vortex manhole will be constructed from in situ reinforced concrete utilising both PVC and GRP to protect the concrete from corrosion caused by the sewer gasses.
The entire project is due to for completion in early 2023.
More News and Articles
Mar 29, 2023
News
Water management: Spain invests nearly 23 billion euros
The Spanish government improves its water management and will invest nearly 23 billion euros to comply with European Water Directives.
Mar 27, 2023
News
UN World Water Day 2023: How municipalities can accelerate the water transformation
The United Nations is proclaiming the motto “Accelerating Change” for World Water Day on 22 March. The message: because the pressure on drinking water reserves is increasing worldwide, the change towards sustainable water use must be accelerated.
Mar 24, 2023
News
Innovative technologies remove pharmaceutical residues from wastewater
Every year on 22 March, World Water Day reminds us of the importance of one of the most important resources of life. Almost two-thirds of our planet is covered with water, but not even three percent is drinkable freshwater. Every …
Mar 22, 2023
Article
Delivering sustainable solutions to solve water challenges
With British Water’s conference on creating a more sustainable water sector approaching, Stephen Kennedy, head of digital and innovation at MWH Treatment shares his views on celebrating recent successes in creating a more sustainable sector while also discussing the challenge …
Mar 20, 2023
News
Supporting the National Water Strategy through scientific research
This month, the federal government of Germany introduced the first National Water Strategy. “With this strategy, the federal government is shining a spotlight on the necessity of integrated water resource management, serving as a leading example of resource use in …
Mar 17, 2023
News
Trenchless manufacturer celebrates installation of 100,000th liner
SAERTEX multiCom®’s trenchless pipe relining product, SAERTEX-LINER, has been installed for the 100,000th time.
Mar 15, 2023
News
Versatile electric pipe-cutter makes UK debut
The first all-electric battery-operated lateral pipe-cutter to enter the UK market has secured sole distribution with pipeline equipment specialist Ant Hire Solutions.
Mar 13, 2023
News
Spring collaborates with Microsoft and Impact X on water innovation
The water sector’s innovation centre of excellence – Spring - is collaborating with Microsoft and Impact X on a new initiative to make tools and funding available for start-ups to accelerate their companies.
Mar 10, 2023
Article
State of Global Water Resources report informs on rivers, land water storage and glaciers
WMO reports on freshwater availability in a changing climate
Mar 08, 2023
News
Australia: Centenarian sewer gets after-dark upgrade
Over 100 years since its inception, Brisbane’s S1 Main Sewer has undergone a seven-year upgrade.
Mar 06, 2023
News
UKWIR gives access to hundreds of water sector research reports
UK Water Industry Research (UKWIR) is providing free access to over 1,000 of its water sector research reports aimed at helping to improve water and wastewater services for customers, and protecting the environment.
Mar 03, 2023
News
Sector must challenge public misconceptions through engagement
The water sector must tackle “unfair criticisms” by sharing more about the great work it delivers, Yorkshire Water’s chief executive, Nicola Shaw, told attendees at British Water’s Better Together reception in Hull.
Contact
Trenchless Australasia
379 Docklands Dr
VIC 3008 Docklands
Australia
Phone:
+61 3 9690 8766