Large Up Size Pipe Replacement Beneath The West Highland Railway
Feb 26, 2013
Replacement by trenchless method » Pipe bursting, in general
A HammerHead® HB125 static pipe-bursting system, provided by U Mole was recently utilised by rail contractor Carillion to undertake an interesting and challenging project to replace a 450mm i.d. clayware sectional culvert running beneath the main railway line between Crianlarich and Oban.
Running at around 5m depth, the 450mm existing culvert needed to be not only replaced but also up-sized to 630mm with the replacement pipe being HDPE. Whilst the project at first appeared to be a straight replacement job, with the need to utilise a 730mm diameter expander behind the bursting head, an equivalent up-size of over 250mm diameter, the installation of the new pipe was not going to be easy.
Although the contractor had used the Hammerhead® HB125 on an earlier section of works on the West Highland rail route, given the massive up-size required for the new installation, operator training of Carillion personnel was completed by U Mole engineers prior to the works on site at project site at Taynuilt.
Other parts of the challenge on the Taynuilt site over and above the up-size required, was access and site preparation. To achieve the replacement installation site works were undertaken for 14 days before the bursting work could commence. This was because ground conditions at the site proved to be soft which meant the footings for the pipe bursting system had to be correctly constructed. The site also required the removal of a line of trees in the rail embankment. These site preparations of the launch and burst site had to be completed with imported stone etc. Also required was the environmental protection of local waterways in case of any hydraulic leaks etc.
Once the site prep was completed the job could be started. Carillion’s workforce was ultimately delighted at the ease of operation of the bursting system once set up. The bursting works, including machine set up were completed over the course of just two days. The actual simultaneous burst run and new pipe installation were actually completed in less than half a working with day no disturbance to the railway line on the embankment above. Looking ahead to a series of future bursts beneath the railway line members of the crew commented that they were looking forward to once again using the HB125 system.
In terms of the site set-up, another complication which was faced by the contractor was ensuring that launch pit face was able to resist the pulling forces of the bursting rig. Carillion’s Section Engineer for the works, Glen Henderson, had to develop a temporary jacking face system which was capable of distributing the pulling force of the rig against the relatively soft railway embankment. Glen said: “Due to the added resistance caused by the expansion process when bursting the existing pipe, the pit face had to be very robust. The set-up ultimately consisted of driven sheet piles with 13 mm (½ in) thick steel road plates.”
Works were carried under the normal working times of the trains. RETB tokens of the OBN2 line between Dalmally station and Connel station were taken and pipe pulling operations to install the new pipe took place between trains. The contractor also continuously monitored the cant and level of the track so that the works could be stopped at the first sign of any movement. The depth of the fill between the pipe installation and the track allowed sufficient consolidation through the embankment such that during the operation no track movements occurred.
Glen went on to say: “Due to the depth of this culvert below the track level, the traditional deep excavation and replacement would not have been feasible. With guidance and training from U Mole we were able to exploit the benefits of trenchless technology. We were able to cut down on our material usage in terms of not requiring substantial amounts of backfill and we minimised our wastage by having no excavated material to dispose of. Any opportunity where we are able to keep the railway open to traffic whilst undertaking this type of work puts us ahead of our competition and allows us to achieve a more economical and sustainable end result for both Carillion and ultimately Network Rail and the service’s customers.”
More News and Articles
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation in the city of Kalundborg, Denmark.
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard Business Review found that “countries …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking water anytime, anywhere.
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating this risk during the design process is an important planning tool to …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, environmentally friendly, time-saving, and cost-effective alternative to open cut methods. The UNITRACC e-learning course "Utility Tunnelling" has been enhanced …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) and the Investment and Development Agency for the Northern Netherlands (NOM) …
Mar 22, 2024
News
A superior HDD offering
Building on its relationships with leading horizontal directional drilling companies, TRACTO Australia has delivered three new rigs to operator Superior HDD.
Mar 20, 2024
News
New portable water filtration technology could improve access to clean drinking water worldwide
The University of Texas at Austin has developed an injectable water filtration system with the aim to aid the over two billion people worldwide who are without clean drinking water.
Mar 18, 2024
News
Global Student Innovation Challenge Calls on Next-Generation Leaders to Tackle Water Security
High School and University Students Worldwide Invited to Expand Water Access and Community Resilience
Contact
Groundforce
Otley Road
HG3 1UD Harrogate
United Kingdom
Phone:
+44 1423 852 295
Fax:
+44 1423 536731