Work on the three components of the Coliban Water-managed interim solution for addressing Bendigo's rising groundwater is on schedule to be completed by mid-2017.
The Bendigo Groundwater Project involves the construction of a 5.4 kilometre pipeline connecting a new groundwater treatment plant at the New Moon Mine in Eaglehawk to a new brine storage lagoon at Coliban Water’s Bendigo Water Reclamation Plant in Epsom.
The Victorian Government has provided $29.77 million in funding to manage rising groundwater in mine voids beneath Bendigo. Coliban Water is delivering the project.
Bendigo Groundwater Project Director David Sheehan said work on the pipeline started in April within the plant and is progressing along Simpsons Road towards Lake Neangar.
“The pipeline construction works have been designed to limit inconvenience to residents. The Simpsons Road section is being built using directional boring, a trenchless technique that minimises excavation and prevents damage to trees and root systems.
“There will be some short-term disturbances for residents, such as traffic management and noise. We have notified residents and will communicate directly with any residents affected as the works progress along Simpsons Road,” said Mr. Sheehan.
Construction work on the groundwater treatment plant and brine lagoon has also been progressing well.
“Around 60 per cent of the plant has been built offsite by our contractor in Adelaide. Onsite construction at the New Moon Mine is scheduled to begin next week.
“Despite the heavy rainfall in April, earthworks for the new brine lagoon are 80 per cent finished. Once the earthworks are completed the lagoon will be lined with polyethylene to make it waterproof.
“The brine lagoon will be capable of holding 270 megalitres, the equivalent volume of 108 Olympic-sized swimming pools,” said Mr Sheehan.
Ward Bros from Rochester are the contractors for the brine storage lagoon, Lendlease are building the groundwater treatment plant and Veolia Water Network are constructing the pipeline.
The pipeline, treatment plant and storage lagoon will deliver a four-year solution to manage the rising groundwater in the Central Deborah Gold Mine and mine voids beneath Bendigo. It is scheduled to be fully operational by mid-2017.
The Department of Environment, Land, Water and Planning is working with community, stakeholders and local agencies to identify a long-term solution for managing Bendigo's groundwater.
For further information and the latest updates see our Bendigo Groundwater Project and Planned works and interruptions pages.
More News and Articles
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, environmentally friendly, time-saving, and cost-effective alternative to open cut methods. The UNITRACC e-learning course "Utility Tunnelling" has been enhanced …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) and the Investment and Development Agency for the Northern Netherlands (NOM) …
Mar 22, 2024
News
A superior HDD offering
Building on its relationships with leading horizontal directional drilling companies, TRACTO Australia has delivered three new rigs to operator Superior HDD.
Mar 20, 2024
News
New portable water filtration technology could improve access to clean drinking water worldwide
The University of Texas at Austin has developed an injectable water filtration system with the aim to aid the over two billion people worldwide who are without clean drinking water.
Mar 18, 2024
News
Global Student Innovation Challenge Calls on Next-Generation Leaders to Tackle Water Security
High School and University Students Worldwide Invited to Expand Water Access and Community Resilience
Mar 15, 2024
News
New water treatment wins Prestigious Award
Introducing a advancement in water treatment, developed by Cardiff University researchers in collaboration with Origin Aqua, the FreeOxTM technology has garnered acclaim by winning a prestigious challenge award at the World Water Tech Innovation Summit. This single-step process not only …
Mar 13, 2024
News
Satellite-based river monitoring technique could provide early warning of flooding
A satellite-based method for monitoring the flow of rivers from orbit could provide a valuable early warning system for flood risk, University of Glasgow researchers have claimed.
Mar 11, 2024
News
Revitalising infrastructure with HDD
Through the use of horizontal directional drilling, TasWater is delivering a new sewer pipeline to improve sewer and stormwater transfer capacity in Launceston, Tasmania.
Mar 06, 2024
News
Picking up the pace on climate action: Building momentum from COP28
At the halfway point of the Paris Agreement, the legally binding international treaty on climate action, average global temperatures are already hitting 1.8°C above pre-industrial levels and future projections are stark. At COP28 in December, we could not escape the reality …
Mar 01, 2024
News
Luminescent sensor detects ‘forever chemical’ pollution in water
Researchers in the UK and Germany have developed a new approach for detecting pollution from ‘forever chemicals’ in water through luminescence.
Feb 28, 2024
Article
BETT installation demonstrating GHG emissions reduction of wastewater treatment
This study presents BioElectrochemical Treatment Technology (BETT) as a new wastewater management solution toward the Net-Zero future. The results reported herein were collected from a BETT pilot system installed at a large brewery in Los Angeles, CA, United States processing …
Contact
Coliban Water
37-45 Bridge Street
VIC 3550 Bendigo
Australia