Midwest Mole Constructing 2,100-ft Tunnel as Part of INDOT Improvements Project
Aug 12, 2019
After years of collaboration between the City of Fishers, City of Noblesville, Hamilton County and Indiana Department of Transportation (INDOT) to address the traffic congestion and public safety challenges along the State Road (SR) 37 corridor, plans are underway to rehabilitate the corridor from 126th Street to 146th Street.
SR 37 is a four-lane, north-south corridor serving the residents of Hamilton County, the City of Fishers and the City of Noblesville in suburban northeastern Indianapolis. It is currently owned and operated by INDOT.
Hamilton County is the fastest-growing county in Indiana. The population of Fishers grew from 7,508 in 1990 to over 90,000 today, and Noblesville’s population grew from 17,655 to over 60,000 in the same timeframe. More than 50,000 vehicles now travel the corridor each day, and they are regulated at each of the cross streets with traffic signals that are becoming more overloaded as time passes.
Using a technique pioneered elsewhere in the region, SR 37 will be converted from a surface street to a freeway by constructing tight roundabout interchanges at existing intersections (plus one larger interchange) and depressing the SR 37 roadway. This allows the road to be upgraded to a freeway with limited displacement and for far less cost than constructing a new freeway.
In advance of SR 37 roadway improvements, infrastructure needs to be constructed to drain water from the newly depressed roadways. In October 2018, Midwest Mole, of nearby Greenfield, Indiana, was given Notice to Proceed on a project to build a 2,100-ft long, 84-in. excavated diameter tunnel for drainage improvements.
Underground Specialist
Midwest Mole is a full-service trenchless contractor that began operation in 1982. The active NUCA member provides a suite of underground construction services to municipal, utility, highway, railroad and private sector clients throughout the United States, including auger boring, microtunneling, pilot tube boring, pipe ramming, pipe jacking, tunneling and horizontal directional drilling.
For the SR 37 project, Midwest Mole’s contract involves constructing the 2,100-ft tunnel from a pit in a residential/commercial area, tunneling eastward to SR 37. As general contractor for the project, Midwest Mole was also responsible for site access construction, as well as a building a detention pond and outlet facility to Shoemaker Ditch.
Midwest Mole elected to use an 84-in. tunnel boring machine (TBM) to construct the tunnel using steel ring beams and wood lagging support. The TBM was supplied by NUCA Sustaining National Partner Akkerman Inc. Upon completion of the tunnel, crews will install 54-in. fiberglass pipe from Hobas Pipe as the final liner, grouted in place with cellular grout.
Because of the length of the tunnel – among the longest the company has built – Midwest Mole made some modifications to the machine. Crews extended the muck conveyor system to about 90 ft to accommodate a three-car muck train, allowing more efficient mucking and excavation.
Additionally, Midwest Mole equipped the TBM with an on-board electric hydraulic power pack. Typically designed for shorter distances, TBMs in this size range are usually powered by an electric hydraulic power pack located in the shaft with hydraulic oil lines installed along the length of the tunnel to power the TBM. An additional benefit to the on-board electric hydraulic power pack was reduced noise in the residential/commercial area.
“We were fortunate that we were able to bring power to the site to help keep it quiet – that was especially important because we were in immediate proximity to residents,” said Mike Liotti, project engineer for Midwest Mole. “In some places bringing power to the site can be a challenge, but in this case there was an existing high-voltage power drop for an ice rink within 700 ft of our main working site.”
Digging Deep
The main work pit was built using trench boxes and is approximately 44 ft long by 14 ft wide. Based on ground investigation, the geology along the alignment was expected to be primarily glacial till – fairly common for the Indianapolis area but also very complex. The till comprises pockets of water and sand and is interlaced with boulders.
“What is interesting about the ground is that there are not connected layers of geology – just pockets of different ground types and groundwater,” Liotti said. “You can be tunneling along and then suddenly you’re in a completely different type of ground in as little as 10 ft. It’s a very challenging environment for tunneling.”
Because of the variable ground, a closed face was specified. While the closed face is helpful in controlling the face of the tunnel in sandy and running conditions, it also makes it more challenging to deal with boulders.
To help break up boulders so they can pass through the cutterhead, crews are using the Micro-Blaster product from EzeBreak. Micro-Blaster, also used by demolition contractors, requires drilling a small hole into the boulder before activating a small blast or series of blasts to break up the rock. The small size of the blast hole eases the task of drilling, especially in cases where a boulder may be encountered in soft ground conditions.
As of late April, crews had mined approximately 780 lf of the 2,100-lf alignment, and have encountered approximately 20 boulders to date. The contract does offer a provision for dealing with boulders in excess of 18 in. in three dimensions: the first 4 hours of dealing with the obstruction are the responsibility of the contractor, while INDOT reimburses the contractor for work beyond 4 hours.
Three manholes are included in the project: one will be at the main work pit, one at the terminus, and one intermediate manhole at approximately 1,300 ft from the work pit. Midwest Mole expects a final completion date of May 2020 for site restoration, etc.
More News and Articles
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation in the city of Kalundborg, Denmark.
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard Business Review found that “countries …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking water anytime, anywhere.
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating this risk during the design process is an important planning tool to …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, environmentally friendly, time-saving, and cost-effective alternative to open cut methods. The UNITRACC e-learning course "Utility Tunnelling" has been enhanced …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) and the Investment and Development Agency for the Northern Netherlands (NOM) …
Mar 22, 2024
News
A superior HDD offering
Building on its relationships with leading horizontal directional drilling companies, TRACTO Australia has delivered three new rigs to operator Superior HDD.
Mar 20, 2024
News
New portable water filtration technology could improve access to clean drinking water worldwide
The University of Texas at Austin has developed an injectable water filtration system with the aim to aid the over two billion people worldwide who are without clean drinking water.
Contact
Midwest Mole
6814 West 350 North
IN 46140 Greenfield
United States
Phone:
+1 317.545.1335