Final double breakthrough at the Emscher sewer
Sep 04, 2017
With the breakthrough of the last two tunnel boring machines into the target pit in Oberhausen-Biefang on June 12, 2017 the tunnel and pipe jacking work for the Emscher sewer has been completed. Over a period of 25 years numerous Herrenknecht tunnelling machines and a wide range of additional equipment were successfully used in the Europe-wide unique environmental and sewage project of Emschergenossenschaft.
With the breakthrough of the two 10 kilometer long main collectors of construction section 40 in Oberhausen the tunnelling work for the construction of the Emscher sewer has been successfully completed. Between October 2014 and June 2017 the two EPB Shields (Ø 3,397 mm) used by construction company PORR achieved genuine peak performances with the support of Herrenknecht service experts. Thanks to their strong teamwork, the site crews were able to keep the average machine availability above 95% over the entire tunnelling period.
The result was outstanding top performances of up to 177 meters per week and up to 582 meters per month, which played a decisive part in the success of the overall project.
The two EPB Shields were the only machines in the entire project using the segmental lining method. With an inside diameter of 2.6 meters, the twin tubes are among the smallest segmentally lined tunnels in the world. The entire tunnelling system with a length of around 85 meters was designed to be accordingly compact. The logistics were also adapted for the small diameter. Thus, for example, a muck removal concept with a locomotive was used, where excavated material was transported in buckets to the shaft and the finished segments were transported to the tunnel face.
One of the special tasks in the realization of construction section 40 was the technically demanding tunnel alignment with several, partially tight curve radii of up to 200 meters. The alignment runs mostly below the A2 motorway and a multitude of inner city supply lines. In addition, an approximately 300 meter long geological fault zone with sandy and groundwater-bearing subsoil had to be passed through. The limited space available at the total of three launch shafts necessitated an optimal logistics concept. For these requirements, solutions were developed in advance and successfully implemented by the site crew during the construction phase.
Work on the overall Emscher conversion project began back in 1992, covering more than 400 kilometers of new underground sewer tunnels. The inhomogeneous ground, the pipe position in up to 40 meter depth, the long pipe jacking distances, the partially complex logistics and the wide range of different construction situations posed particular challenges in the creation of the necessary tunnel structures.
Over almost 25 years the contractors relied on Herrenknecht's project-specific tunnelling technology for the underground excavation work in construction sections 20, 30 and 40. This included numerous AVN machines for pipe jacking in the smaller diameter range, EPB Shields using the pipe jacking and segmental lining methods as well as a Vertical Shaft Sinking Machine or VSM to sink a 23 meter deep launch shaft.
Over 60 kilometers of the main and secondary sections were built by contractors using Herrenknecht tunnelling technology. In individual construction phases, Herrenknecht Group partners supported the quick overall construction process. VMT supplied TBM navigation systems as well as various communication, data management and safety systems. Herrenknecht Formwork produced segment moulds and MSD supplied rolling stock, a lifting beam and a tilting table for the pipe plant in Gelsenkirchen.
The Emscher, whose source rises in Holzwickede to the east of Dortmund, passes through a series of cities in the German Ruhr area on its 80 kilometer path before it flows into the Rhine. Since the beginning of industrialization around 1850, the small lowland river was used as an open channel for sewage, flood and rainwater and degenerated into the dirtiest river in Europe. With the renaturation of the stream, one of the main tasks of the Emschergenossenschaft founded in 1899, in future sewage and rainwater will be separated again, drained away underground and purified in intermediate treatment plants. As a result the river will become clean again in the long term and the quality of life of the people in the Ruhr area will increase. Commissioning of the 51 kilometer long Emscher sewer is planned for the end of 2020.
Project data - Final double breakthrough at the Emscher sewer
MACHINE DATA M-1856/M-1857
Machine type: 2x EPB Shield
Excavation diameter: 3,397 mm
Max. torque: 1,600 kNm
PROJECT DATA
Tunnel length: a total of 2x 10,000 m
Lining method: Segmental lining
Application: Sewage › Geology: Emscher marl, sand
Contractor: PORR AG Austria
Client: Emschergenossenschaft
More News and Articles
Apr 19, 2024
News
WATCH: Overnight with SAERTEX-LINER H20 in São Paulo
Available through Pipe Core, high-quality liner SAERTEX-LINER H20 performed under pressure in São Paulo, Brazil.
Apr 17, 2024
News
Immersive media provides wastewater experience in Denmark
An immersive media experience (IMX) may not be what most people want when they think about industrial wastewater, but that is exactly what visitors can expect when they visit a new installation in the city of Kalundborg, Denmark.
Apr 15, 2024
News
Spotlight on gender diversity at Pipe Core
Since founding in 2008, Pipe Core’s team has grown across all areas of the business and is now in a position where there are more females than males across the organisation. Research published in Harvard Business Review found that “countries …
Apr 12, 2024
News
New Wave of Startups Scale Innovation to Solve Global Water Challenges
Innovators from Around the World Join Xylem’s 2024 Accelerator Program to Deploy Breakthrough Innovations for Utilities and Industrial Users of Water
Apr 08, 2024
News
Integrated sustainable electricity and clean drinking water systems
Altitude Water and New Use Energy Solutions have partnered to create integrated, mobile solar-plus-water generation systems that produce sustainable electricity and clean drinking water anytime, anywhere.
Apr 05, 2024
News
How to Evaluate Hydraulic Fracture Risk in HDD Design
The design of horizontal directional drill (HDD) installations often requires an evaluation of the potential for hydraulic fracture of the soil layers through which an HDD passes. Evaluating this risk during the design process is an important planning tool to …
Apr 02, 2024
News
Historic Project Linking Rome and Vatican City Uses Advanced Technology and Local Knowledge to Keep Water Flowing
Relocation of Major Sewer Infrastructure Enables Construction of Pedestrian Link for 35 Million Visitors to the 2025 Jubilee
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, environmentally friendly, time-saving, and cost-effective alternative to open cut methods. The UNITRACC e-learning course "Utility Tunnelling" has been enhanced …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) and the Investment and Development Agency for the Northern Netherlands (NOM) …
Mar 22, 2024
News
A superior HDD offering
Building on its relationships with leading horizontal directional drilling companies, TRACTO Australia has delivered three new rigs to operator Superior HDD.
Mar 20, 2024
News
New portable water filtration technology could improve access to clean drinking water worldwide
The University of Texas at Austin has developed an injectable water filtration system with the aim to aid the over two billion people worldwide who are without clean drinking water.
Contact
Herrenknecht AG
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 7824 302-5400