Milestone for Hard Rock Tunnelling: Final Double Breakthrough Follo Line
Apr 24, 2019
The construction of Norway's longest railway tunnel marked a breakthrough for the use of tunnel boring machines in hard rock tunnelling.
In Scandinavia long rail tunnels have hitherto been drilled and blasted rather than bored. In the Follo Line Project, the tunnel boring machines made a convincing case for themselves all the way through the extremely hard Norwegian rock.
Four tunnel boring machines (TBMs) by Herrenknecht worked simultaneously to excavate the main part of two 20-kilometer railway tunnels between Oslo and Ski.
In February 2019, the final double breakthrough of the Double Shield TBMs "Anna" and "Magda" successfully completed the challenging mission and drew a spectacular close. The final double breakthrough of the two Herrenknecht tunnel boring machines "Anna" and "Magda" (Double Shield TBM, Ø 9,900 mm) in the Norwegian Ski completed the excavation of both 20-kilometer-long tunnel tubes of the Follo Line railway.
This concludes the tunnelling work on what is currently the country's largest infrastructure project. The first two Herrenknecht-TBMs had already reached their destination in opposite Oslo on September 11, 2018.
The miners and the 350 invited guests cheered loudly when, on the afternoon of February 26, 2019, the sister machines cracked the last few centimeters of hard Norwegian rock with maximum precision after they had worked their way through it for about nine kilometers each. "Anna" and "Magda" had been chewing through extremely hard Norwegian gneiss since autumn 2016. This successful completion of the project represents an important milestone for tunnel boring machines in a country that has so far been relying primarily on conventional drill and blast tunnelling.
"If we want to stay fit for the future, we can't just say: we'll do it the way we've always done it," says Anne Kathrine Kalager, project manager for Bane NOR. "We must always keep looking for the best methods – and as it turns out, in this project TBMs have decisive advantages."
With drill & blast it would have taken a total of seven construction sites in the metropolitan area, some of them difficult for trucks to access, which would have placed a great burden on traffic and residents. In contrast, the TBM solution gets by with only one central point of attack. Two 900 meter long access tunnels connect the large Åsland jobsite on the surface with two underground caverns.
From there, two machines each bore south and north respectively to create the two tunnel tubes. Kalager is expecting the Follo Line to act as a signal for further projects in Norway.
Acciona Ghella Joint Venture is commissioned by the Norwegian government’s agency for railway services (Bane NOR) to construct the main part of the tunnel at the Follo Line (EPC TBM). As of late 2022, high-speed trains are to drive through the new tunnel tubes at speeds of up to 250 kilometers per hour, halving the travel time between Oslo and the municipality of Ski 22 kilometers to the south from 22 to 11 minutes.
The Follo Line represents a lifeline for the future of the Norwegian capital with its population of 600,000 and the region around Ski, which anticipates population growth of 30 percent by 2025.
To master the extremely hard rock with up to 300 MPa compressive strength, Double Shield TBMs by Herrenknecht were employed. The technically very sophisticated tunnel boring machines combine the functional principles of Gripper and Single Shield TBM in one machine. They can simultaneously bore and line the freshly bored tunnel with rings made of reinforced concrete segments - 140,000 of these segments were placed during the Follo Line Project.
The advance stands and falls with the quality of the disc cutters. The disc cutters made of special steel, 19 inches in diameter and each weighing up to 372 kilograms, are pressed against the extremely abrasive rock with up to 32 tonnes of pressure. "The wear of the disc cutters was enormous," stresses Matthias Flora, a specialist in hard rock at Herrenknecht.
Up to 50 of Herrenknechts cutter experts in Schwanau professionally refurbished a total of around 8,000 worn disc cutters for reuse for the four machines in Norway over the entire project period. "In close cooperation with our customers we feel our way ever closer to the optimal parameters for the disc cutters," Flora explains about the special project challenges.
"Even the tiniest improvement to the discs counts. If optimal cutter management allows us to complete just one more tunnel ring per day and machine, this ultimately adds up to put us two to three months ahead of the planned project time." states Fernando Vara, Project Director of the Acciona Ghella Joint Venture.
Thanks to regular maintenance and excellent teamwork, consistently high advance rates and peak performances of up to 155 meters per week were achieved in Norway. Such advance rates can only be achieved with particularly strong and robust machines. Each of the four cutterheads weighing 265 tons was driven by 13 engines with a drive power of 4,550 kW each, which corresponds to 475 hp each.
Project data Milestone for hard rock tunnelling: Final double breakthrough Follo Line
MACHINE-/ PROJECT DATA S-980, S-981, S-982 AND S-983 – FOLLO LINE
Machine type: 4x Double Shield TBM
-
Shield diameter: 4x 9,900 mm
-
Drive power: 4x 4,550 kW
-
Advance length: 1x 8,881 m 1x 8,892 m 1x 9,113 m 1x 9,128 m
-
Geology: Hard rock, gneiss
-
Client: Bane NOR
-
Contractor: AGJV Acciona Ghella Joint Venture
Herrenknecht AG
Herrenknecht AG is the only company worldwide to deliver tunnel boring machines for all geologies and in all diameters – ranging from 0.10 to 19 meters. The product range comprises tailor-made machines for traffic, supply and disposal tunnels, technologies for routing of pipe lines, as well as additional equipment and service packages. Herrenknecht also manufactures drilling equipment for vertical and inclined shafts as well as deep drilling rigs.
More News and Articles
Mar 27, 2024
News
USU Study Looks at Water Main Break Rates in the U.S. and Canada
Report Highlights Correlation Between Material and Diameter
Mar 26, 2024
News
Update BE-21: New Material in Course and Modules on Trenchless Pipe Installation
Online training on the topic of pipeline installation in civil engineering: Trenchless technology for underground drainage construction can be a resource-efficient, environmentally friendly, time-saving, and cost-effective alternative to open cut methods. The UNITRACC e-learning course "Utility Tunnelling" has been enhanced …
Mar 25, 2024
Article
Bacteria as a new weapon in wastewater treatment
In early November, San Diego based startup Aquacycl officially opened its first European office and test center at the Water Campus in Leeuwarden. The Netherlands Foreign Investment Agency (NFIA) and the Investment and Development Agency for the Northern Netherlands (NOM) …
Mar 22, 2024
News
A superior HDD offering
Building on its relationships with leading horizontal directional drilling companies, TRACTO Australia has delivered three new rigs to operator Superior HDD.
Mar 20, 2024
News
New portable water filtration technology could improve access to clean drinking water worldwide
The University of Texas at Austin has developed an injectable water filtration system with the aim to aid the over two billion people worldwide who are without clean drinking water.
Mar 18, 2024
News
Global Student Innovation Challenge Calls on Next-Generation Leaders to Tackle Water Security
High School and University Students Worldwide Invited to Expand Water Access and Community Resilience
Mar 15, 2024
News
New water treatment wins Prestigious Award
Introducing a advancement in water treatment, developed by Cardiff University researchers in collaboration with Origin Aqua, the FreeOxTM technology has garnered acclaim by winning a prestigious challenge award at the World Water Tech Innovation Summit. This single-step process not only …
Mar 13, 2024
News
Satellite-based river monitoring technique could provide early warning of flooding
A satellite-based method for monitoring the flow of rivers from orbit could provide a valuable early warning system for flood risk, University of Glasgow researchers have claimed.
Mar 11, 2024
News
Revitalising infrastructure with HDD
Through the use of horizontal directional drilling, TasWater is delivering a new sewer pipeline to improve sewer and stormwater transfer capacity in Launceston, Tasmania.
Mar 06, 2024
News
Picking up the pace on climate action: Building momentum from COP28
At the halfway point of the Paris Agreement, the legally binding international treaty on climate action, average global temperatures are already hitting 1.8°C above pre-industrial levels and future projections are stark. At COP28 in December, we could not escape the reality …
Mar 01, 2024
News
Luminescent sensor detects ‘forever chemical’ pollution in water
Researchers in the UK and Germany have developed a new approach for detecting pollution from ‘forever chemicals’ in water through luminescence.
Feb 28, 2024
Article
BETT installation demonstrating GHG emissions reduction of wastewater treatment
This study presents BioElectrochemical Treatment Technology (BETT) as a new wastewater management solution toward the Net-Zero future. The results reported herein were collected from a BETT pilot system installed at a large brewery in Los Angeles, CA, United States processing …
Contact
Herrenknecht AG
Achim Kühn
Head of Group Marketing and Corporate Communications
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 7824-302-5400
Fax:
+49 7824-302-4730